JAMPA | Mar 10 | Chief Minister Pema Khandu today directed NEEPCO authorities to accelerate completion of 110-MW Pare Hydro Electric Project here toeing its schedule to go for trial spinning of turbines by month end for its commissioning.
Khandu, who along with Deputy Chief Minister Chowna Mein, Speaker T N Thongdok, Deputy Speaker Tumke Bagra, host of ministers and legislators, including Power Minister Tamiyo Taga and UD Minister Nabam Rebia, escorted by NEEPCO officials, visited its sites here and at Sopo to take stock of the progress.
The project started in 2010 was originally scheduled to be completed by August 2012, but revised to December 2017. But, heavy machineries couldn’t reach the project site due to ongoing construction of Trans-Arunachal Highway that caused the delay.
Khandu assured that it would be ready for commissioning by March 31 next but take few more months to generate power in full capacity.
The team visited dam-site here where the Works of the run-of-the-river project are on in full swing at Jampa where proposed concrete gravity dam of 63 meters tall and 134.257 meter long would be built over River Dikrong. The 1.029-km long tunnel would bring water from the dam storage to its power house at Sopo, 3-km downstream. It also inspected turbine area of the power house.
Expressing his satisfaction over the progress despite several hurdles, like monsoon-triggered landslides and floods, Khandu assured logistics and administrative support to NEEPCO for its commissioning.
Terming it as an important project to benefit state people, Khandu said it is a matter of great satisfaction that at least one of the several hydro projects is going to be operational within a month,” he said while interacting with local villagers.
Khandu asserted that 2% free power – one each from the state share and 1 from project developer – would be utilized for local area development, which would be huge. He congratulated the locals for sacrificing their land but time has come for them to reap the benefits.
Khandu also laid foundation stone of a bridge over Dikrong that would connect Sopo with Lekhi village on the right-bank. A hanging-bridge built by local villagers provides link now. He assured fund for the bridge, which would be shared by NEEPCO under its corporate social responsibility.
Responding to a plea for CC road from the bridge, the CM assured provisions in ensuing budget. (CMO)
AONS adds: State governor on Friday in his customary address to the budget session had hinted that two HEPs including Pare would be commissioned within next two months.
CM-led team visits Pare HEP, to be operational by Mar 31
JAMPA | Mar 10 | Chief Minister Pema Khandu today directed NEEPCO authorities to accelerate completion of 110-MW Pare Hydro Electric Project here toeing its schedule to…https://t.co/vm2fNqiPcY pic.twitter.com/AdspyGMupj— Arunachal Observer (@ArunObserver) March 10, 2018