36-month completion target: TKE
TKE project engineer Sudhir Kumar, when contacted, told this daily that the road up to Potin is already complete, while the rest 108-km from Joram to Koloriang (less 18-km being executed by BRO) is being executed by TKE under six packages whose wroks started in February last.
However, land is yet to be handed over for package-I & II in Lower Subansiri district while 60% land has been handed over in Kra-Daadi and Kurung Kumey districts. About 15-km road is complete against all odds while 10-km in multiple stretches of packages III to VIII is in progress against all odds, he said.
Works could not be started in some patches of the built up areas due to various reasons, like non-removal of existing structures including electric poles, water pipe lines, public utility services etc by respective district administration besides land disputes causing hindrances, he rued, adding once lands are handed over free from encumbrance, the works would progress very fast for which men and machineries are already deployed at the site.
By Pradeep Kumar
ITANAGAR, Oct 05: Speed is synonymous to development toeing common adage ‘gati hi pragati’, which is far from a reality in Arunachal Pradesh for lack of proper road connectivity to most of the far-flung areas.
Why is so even after 31 years after attaining statehood and 71 years after independence? Perhaps, former Deputy Prime Minister L K Advani was right in his revelation in his Itanagar public address in 2003 – “Delhi had decided not to develop Arunachal after the 1962 Chinese aggression, fearing it could benefit the neighbour. It was a historical blunder. But Arunachal Delhi se door hey, par dil se nahin”.
However, it was former chief minister Dorjee Khandu, who had motivated then Prime Minister Dr Manmohan Singh to visit Itanagar on 31.01.08, after 12 years by any PM to visit Arunachal. Dr Singh had announced a huge economic package including Tarns-Arunachal Highway (TAH) to provide double-lane blacktopped road link to all district HQs.
Works on TAH still continue even after a decade and 164-km Itanagar-Palin road is part of the TAH. It was very difficult to drive any vehicle along the dilapidated, mud filled road with ponds all along posing serious threat by hidden rocks to hit hard below any vehicle. It took about 9 hours to Palin, headquarters of Kra-Daadi district, on October 2 on an Innova car, and same time on return.
When the car got struck by rocks many times while it skidded off the road by Pritam Singh managed to control. However, at one point, a local coming from opposite direction on an Alto said that the road was better but works by M/s T K Engineering Consortium Pvt Ltd deteriorated its condition and aggravated further by the rainy season. However, we the people of Kra-Daadi are hopeful that completion of the road would offer seedy and pleasant drive to and from state capital while enjoying the natural beauty along the road.