ITANAGAR, Nov 02: Chief secretary Satya Gopal took stock of status and progress of Saubhagya scheme in the State in a review meeting on Pradhan Mantri Sahaj Bijli Har Ghar Yojana-Saubhagya here on Friday.
Gopal, addressing power commissioner G.S.Meena, Rural Electrification Corporation Ltd ED G.S.Bhati, state nodal officer Ogom Moyong, all CEs, SEs & EEs, raised concern over present pace of delivery of materials by RECPDCL and requested the ED to deliver entire materials by November 15 next.
Taking account of readiness of power department to achieve 100% household electrification in the state, he urged the department concerns to work on mission mode to achieve the GoAP objective to provide last mile free electricity connections to all un-electrified households in within December 31 next.
It was decided the required materials in higher altitude and difficult terrains will be transported on priority within week’s time from the date of delivery of materials by RECPDCL in base stores. The materials available will be installed in such a way that maximum HH connections are released with minimum additional infrastructure.
Village-wise separate installation teams for high tension, low tension, distribution transformer and household works are kept on standby so that the said works are completed within week’s time from the date of receipt of materials at site.
The ED informed that as on date 20% materials are delivered at pre-designated base stores by RECPDCL and the rest in transit will be delivered November end.
But Gopal directed the power department to ensure 100% household kits are installed by December 15 next and instructed all engineers for full utilization of materials supplied by the REC to achieve the goal. The progress work of each division shall be monitored by APDA and submit regular report to the CS and CMO, he directed. (PRO)