ITANAGAR |May 03| The residents of both sides of NH-415 have been confused on receiving two court notices on same subject has created confusion. were so go ?.
Chandranagar-Banderdewa portion of the NH proposed to be converted to four-lane as approved by Union MoRTH.
Chandranagar-Papu Nallah (Jully tri-junction) to be taken up in the first phase for which the ministry has allocated fund that has intensified the preparatory works.
The MoRTH notified highway administrators on April 5 last who in turn have begun issuing notices to affected people whose structures were falling with the right of way (RoW) or who have encroached the RoW. In all 1084 affected people were identified including those encroachers, according to head of highway administration CEO-cum-ADM Talo Potom.
Notices were issued to encroachers and others after structures were marked by the authority for hearing to begin from April 20 last in CEO-cum-ADM copurt, but reportedly notices from Itanagar EAC were also received by many creating confusion about where to report for hearing.
With such confusion, the affected people approached both office and hearing began at both courts for the same subject. But besides confusion, people have been confronting inconveniences to attend two courts on specific date and time.
When asked, Potom said: “I being CEO-cum-ADM and chief highway administrator am duty bound for Chandranagar- Banderdewa stretch falling under my jurisdiction. The interest and concern shown by DC in clearing illegal structures is appreciable”.
However, Bomjen said that the hearing in his court aimed at working out demolition cost of asset falling within RoW along Itanagar-Chandranagar-Shiv Mandir point. It will help the asset owners as if they demolish themselves after obtaining a ‘self declaration’. The process begun on April 28 last and 20 building owners so far have submitted their willingness through self declaration against notices issued to 114 out of total 400.
After CEO court circulated April 6 Capital DM order for eviction drive along NH-415, Itanagar EAC-cum-estate officer issued so cause notice under Arunachal Pradesh Public Premises (Eviction of Unauthorised Occupant) Act 2003 to all owners.
When contacted, Potom said that the people were confused after EAC issued so cause notices while other by Capital DC. Thus, considering the request and difficulties, Potom said he differed hearing in his court till eviction process along with compensation issues are resolved EAC and CO concerned as directed by DC.
However, Potom admitted his ignorance about two notices but said that EAC served notices as directed by Capital DC.
Meantime, Capital district administration has began distributing compensation to total 116 land affected people of Chandranagar-Papu Nallah portion. The total compensation amounted to Rs 15,12,76,807.