HOLLONGI, Sept 07: Doimukh MLA Tana Hali Tara with several officials visited green field airport site here on Saturday to review progress of work and discussed steps to rehabilitate 156 Chakma families, who would be displaced from the proposed airport site.
The delay in shifting them has been creating hurdle in work progress of the ambitious project. The team was told that the estimate for relief & rehabilitation (R&R) has already been submitted to the GoP by Papum Pare DC through land management secretary a week ago.
However, the district administration was waiting for fund to implement the R&R plan to shift those 156 Chakama families, DA official said.
Earlier the Chakma families had lodged a complaint with National Human Right Commission (NHRC) against their arbitrary eviction from their temporary settlement area without any rehabilitation package. The GoAP had before the NHRC to assure that displaced families will be first rehabilitated with before commencement of the airport project works and based on which the case was closed.
The Chakma Rehabilitation & Resettlement Committee, in a memorandum submitted to local MLA and Papum Pare DC Pige Ligu on Saturday, urged the GoAP to rehabilitate them soon for the airport work to resume soon.
Moreover, land acquisition for four-lane approach road towards airport has not been taken up due to non submission of approved strip alignment plan by PWD (Highway) division to the district administration. It was informed that GoAP has not finalized the executing agency for the work.
Airport Authority of India (AAI) officials, who were present, riefed that last date for the submission of tender for Hollongi airport project is September 9 which will be opened next month. Oo bidders participated in first tender process forcing them to go for second round, the AAI officials said.
MLA Tara thanked Chief Minister Pema Khandu for prioritized sanction of the airport project with active support of Union MoS Kiren Rijiju.
It may be recalled here that Union MoS (Independent) for Civil Aviation Hardeep Singh Puri, during a videoconference with state chief scretary Naresh Kumar recently had fixed 31.03.2022 as completion date for green field airport project.
Besides DC Ligu and officials of line departments, like EEs of PWD (Highway), PHE&WS, Doimukh PWD, Poma division RWD & power, DLRSO accompanied the MLA.