PALIN, Jan 20: Home Minister Bamang Felix expressing concern over slow work progress of Joram-Koloriang stretch of Trans-Arunachal Highway (TAH-under package 1 to 8 of Joram to Koloriang) here on Monday directed contractor T.K. Engineering Consortium Pvt Ltd (TKE) to speed up work.

Felix was reviewing status of that stretch in a meeting, attended by Kara Daadi DC, SP, DySP, PWD, power, PH&WS EEs, DFO, DLSRO, TKE nodal officer & NHIDCL GM, when TKE nodal officer committed to engage more manpower, machineries & resources by February 20 next and the HM asked the DC to confirm it.

He also directed DLRSO and departments concerned to shift to remove all utility related hindrances from ROW of that stretch by February 28 to ensure work progress.

The issues relating to TAH Victim Committee stopping work were deliberated when the HM said that question of victimization doesn’t arise when the road would benefit the masses and urged district administration to tackle such protest amicably. (DIPRO)