By Pradeep Kumar
NAHARLAGUN, Jun 07: Arunachal Pradesh is known for its communicational hazard, which intensifies during rainy days as Kurung Kumey and Kra-Daadi districts people are still deprived of their monthly ration rice with dozens of ration rice-laden trucks are stuck in feet-deep muddy 141-km Panya to Koloriang road.
Young entrepreneur Bengia Bado, who returned from Koloriang on Friday, produced photographic evidences about many trucks stuck in totally dilapidated muddy road and struggling to proceed ahead. He informed that the contractors of that road engaged by MoRTH’s National Highways and Infrastructure Development Corporation have failed to develop that stretch of road.
On the other hand, 17-km Joram-Panya has been built very well by the BRTF of Project Arunanak, he said and advocated that Panya-Koloring road should also be given to Project Arunanak for immediate maintenance.
Appreciating present state government led by Chief Minister Pema Khandu for attaching importance to road and infrastructure development in the state, Bado said that roads hold key to development of this land-locked state for which it deserves top priority treatment, particularly for movement of ambulance carrying patients.
The Project Arunanak headed by chief engineer Brig AS Chonker has won five commendation certificates for building Daporijo bridges, one each for Koloriang-Huri axis and Lemiking-Taksing axis roads with quality and short time against all odds, he said, adding if the CM asks Project Arunanak for renovating that road, Brig Chonker with his good relation would execute it through the BRTF.
Head load best alternative: Reacting to the fact that the public distribution system (PDS) and ration card holders of those districts were caught between the devil and the deep sea, Civil Supplies & Consumer Affairs Minister Kamlung Mosang said that the road does not belong to his department. Even if the state government sanctions fund for renovation, it may take six to 12 months as monsoon rains have started, he reasoned.
But, head load or porter system in far-flung or inaccessible areas of the state, particularly in 12 air-fed stations, could be the best alternative, he said, adding that he has been proposing such system to the MoRTH to carry PDS rice since 2018. This was also proposed to Union Food & Public Distribution Consumer Affairs and Trade & Commerce Minister C. R Choudhary when he had visited state capital but no outcome as yet, he said.
Pointing out that airdropping by An-32 aircrafts causes about 70 to 80% losses of rice whose airfare per quintal is Rs 16,000 against head load or porter system rate of Rs 8,000 per quintal, he said that clearly indicate that which system should be adopted.
The 158-km Joram-Koloriang road being the lifeline for both districts should be trafficable round the year for not only transportation but emergency movement, particularly by patients, said All Arunachal Pradesh Panchayat Parishad secretary general Sangha Tagik, adding the road should be repaired forthwith.