1 unit of Kameng HEP commissioned: DyCM

ITANAGAR, Jun 19:   One unit of 600 MW Kameng Hydro-Electric Project (4X150 MW) was commissioned for commercial operation by North Eastern Electric Power Corporation Limited on Wednesday last.

With its commissioning, Arunachal Pradesh will receive 13.83%, i.e., 20.75 MW besides 12% free power and remaining 1.83% as allocated share, according to Deputy Chief Minister Chowna Mein, in-charge of Power & Renewable Energy Resources.

The second unit is likely to be commissioned within a week while other two after repair of penstock but within this fiscal year.

After commissioning of four Kameng HEP units, the state will receive a share of 83 MW. The HEP besides generating revenue would offer employment opportunities to educated youths and promote industrialization, Mein added. (PRO)