From Our Correspondent
TEZU, July 24: Darkness has plunged Lower Dibang Valley, Lohit and Namsai districts since breakdown of 132 KV Pasighat-Roing-Tezu transmission line since July 20 last.
The flooded Dotung River under Dambuk circle eroded the bank that led to fear for collapse of transmission tower. Though restoration works have been continuing since then and likely to be completed soon to restore power supply, official sources said.
The normal supply could be given anytime with the stringing of single conductor, said Lohit power division EE Hage Gumto.
Moreover the 33 KV line from Rupai in Assam has also breached by flood water at Digaru for which repair works have been taken up, he added.