TEZU, Dec 18: The high potential Tezu Airport is expected to be made operational in May 2021 as prerequisite amenities for landing of the ATR are in war footing.
Several mandatory facilities, including terminal building, car parking, entry and exit points, for its smooth functioning are under construction against all odds to maintain timeline of May 21, given by Union Ministry of Civil Aviation by, Airport Authority of India (AAI) office said.
Strategically located Tezu & Pasighat Airport has been given top priority along with special impetus from the Ministry.
“The ATR, 72-seater planes would offer three-day weekly service with a scheduled three routes of Guwahati-Tezu, Tezu- Guwahati-Imphal, Tezu –Guwahati-Rupsi-Kolkata respectively, sources said.
Under fourth round of bidding under the Ude Desh ka Aam Nagrik (UDAN) would make flying more affordable.
“With focus on connectivity of NE, UDAN 4.0 scheme under the MoCA has invited bids There are six underserved and 24 unserved airports/airstrips in the North East,” an official release said.
The underserved airports and airstrips in the list are at Pasighat and Tezu (Arunachal Pradesh), Jorhat, Rupsi and Tezpur (Assam), and Shillong (Meghalaya).
Meanwhile, Tezu Airport officials expressed concern over dilly dallying tactic for clearance of four acres of land allotted to Airport for residential purpose. The officials have urged Lohit district administration to sort-out land which has been made controversy by some local populace.
“We are in want of secure accommodation, presently we managed some resident on rent but if we owned our land we can build up residential complex with security and comfort for our staffs”, says one of the AAI officials, and pleaded for 1. 5 acre of additional land for developing other amenities requisite for the landing ground.