BRO mirrors ingenuity: Smooth ride to Indo-China border, makes 1962 a passé after 58 years

  • 99% road in bad shape: Minister

By Pradeep Kumar

ITANAGAR, Jan 03: Amidst prevailing tense situation along Indo-China border with increased movement of the PLA in China side of Asaphila and Taksing region in Upper Subansiri district of Arunachal Pradesh, the officers and officials of Border Roads Organisation (BRO)’s Project Arunank have been making relentless efforts to build roads to enable defence forces to boost their operational capability.

In October 1962, China had intruded into Indian Territory through Arunachal Pradesh to entire the Tawang and West Kameng sector and proceeded up to Tezpur in Assam when Indian Army had a humiliating defeat for want of roads to border areas. As Beijing’s Indian policy, which I term as ‘do’s tail’ for beyond concept to predict its movement, it is but natural for central government to take a call on this issue for national security.

Thus, road construction activities are going on in full swing, a highly placed official source told this editor on condition of anonymity, adding the riding surface in the above area has drastically improved. The Team Project Arunank, as directed by BRO Director General Lt Gen Rajeev Chaudhry, would complete all targeted projects in this area within next few months reflecting its commitment by “either finding a way or make one”.

It may be recalled here that lack of road to 45-km Tama Chung Chung (TCC)-Taksing axis in Upper Subansiri district had been posing tough challenges to maintain supply line to thousands of Army and para military forces guarding sensitive Indo-China border along the Line of Actual Control (LAC), being maintained by helicopters only since independence. The China Study Group (CSG), therefore, had approved this strategic TCC-Taksing road in disturbed Asaphila region and assigned its construction to Project Arunank to facilitate easy movement of defence forces as well as civilians living in those areas.

However, the alignment of road in Upper Subansiri Valley passes through dense forest, rocky hill face, extremely narrow, steep mountainous slopes, 80% hard rock strata, punctuated by thinly populated tribal hamlets. The area along the bank of Subansiri River at altitudes ranging from 1,915-m to 2,540-m receives average annual rainfall of 300-400 cm. Thus, this sector is considered to be one of the toughest areas of all BRO projects because of extreme climatic conditions, unpredictable weather and negligible development including telephone connectivity.

The TCC-Taksing road was linked earlier from nearest town by constructions of different sectors as depicted in the picture. This road is the lifeline of all border villages in the district and serves as the only link for tourist attraction for rapids of Subansiri River and famous Takpasiri Budhist Pilgrimage route.

However, heavy equipments were airlifted by helicopter to Reddi and Taksing to ensure three-prong formation cutting and Taksing was connected in 2018. After the TCC-Taksing road was linked there was enormous pressure on Project Arunank to make the road worthy for vehicular traffic in order to enhance logistics and supply of defence stores till Taksing and connect border areas with the main land.

The construction of extra wide bailey bridges and other works begun in August 2019 as a prelude to surfacing works, which begun but gaining speed posed problem for continuous vehicular movement in this area having  poor infrastructure and communication. Only limited resources could reach this area initially for which construction of culverts and drainages was a herculean task. However, meticulous planning for supply of materials, adopting new technology for cementatious surfacing works, precast culverts, gabion structures for slope stabilization, aerial reconnaissance by Drone for preparation of estimates and monitoring purposes led to successful construction of the road by 23 BRTF.

Therefore, 128 RCC in last one year has built 10 extra wide bailey bridges along TCC-Taksing road, almost one bridge per month, despite continuous rainfalls, flooding of streams, intermittent landslides, limited time for shifting of huge quantities of bridge material from long distances. And the bridges were launched in record time with out of the box innovative solutions.

Arunank chief engineer Brig A S Chonker directed by Lt Gen Chaudhry to accelerate work progress gave a new thrust to adopt pre-cast culverts, which the BRO implemented for the first time in such a remote border area to help meet completion deadline. The completion of road works in record time has reduced time by approximately 3½ -hour for vehicular movement up to Taksing now, which was 7-houor in September 2019. The continuous improvement works of formation widening, permanent works followed by surfacing works are being executed in full swing to always facilitate pleasure ride s along the Indo China border.

However, present Nacho MLA-cum-Tourism and Transport Minister Nakap Nalo, who represents Taksing area in state Assembly, expressed his strong resentment, saying that “almost 90 percent road from Daporijo to Taksing is in very bad shape. The BRO should take bold steps to improve the defence road further for use during any national emergency”.