Slow progress of Vijoynagar road irks DyCM

ITANAGAR, Jan 04: Deputy Chief Minister Chowna Mein expressed dissatisfaction over slow progress and inordinate delay in completion of strategic 157-km PMGSY road from Miao to Vijoynagar while reviewing its status with UD, Food Civil Supplies Minister- cum-local MLA Kamlung Mosang and RWD Minister Honchun Ngandam  here on Monday.

Justice has not been done to Vijoynagar people of as we had promised them an all-weather road connectivity since very beginning of their settlement in this remote administrative headquarters, he said and assured all possible support of the state Govt. He exhorted the executing agencies and contractors to speed up works by putting all resources together.

The PMGSY road was sanctioned in five parts I first part in 2014 and till now Part I (12.5-km) & II (14.5-km) have been completed,  work under Part III (34-km) & IV (80-km) are in progress while Part V work is yet to be start.

Attributing difficult terrains coupled with landslides at several locations, marshy lands, unfavourable climatic conditions and short duration of working period to the delay, the executing agencies have informed that December 2021 has been fixed as completion target.

Among others, RWD Secretary N T Glow, MGSY chief engineer (P) D Nyodu and Changlang RWD EE Nyamar Rike were present. (PRO)