Cyclone hits Tezu, disrupts power supply

TEZU, May 15: Acute power crisis hit Tezu Township since Friday due to cyclone that hit hard the township which uprooted trees snapping both the HT & LT line in and around the town.

Uprooted trees completely damaged the service line along the The NH-13 especially, from medical to Dagrebaba point. The quantum of damage was maximum at Kanchi Charali, NH road to Telluliang and Tamlanagar villages.

The trail of devastation is massive even though the administration has pressed men and machinaries on war footing to restore the system. To meet up power crisis at Zonal Hospital and Covid Care Centre at botanical garden, DG sets have been used, EE Power Hage Gumto informed.

Meanwhile, the 132 KV line in between Pasighat – Roing would remain non-functional due to shifting of tower from May 17. The Power Grid has deployed men and materials to create Emergency Restoration System (ERS) to build tower at safer place to avoid upcoming monsoon threat.

The Lohit Power Division infromed that the affected districts would be managed from 33 KV Rupai Line till the restoration of 132 KV.

According to the Arunachal Pradesh State Load Dispatch Centre (APSLDC), the first phase of the shutdown will be from May 17 to 18, the second from May 20 to 21 and the third from May 23 to 24.