New road to Poma source, abutment work begin: PHED

Restoration of water supply

 

By AO News Service

ITANAGAR | Jul 21 | PHED swung into action today to expedite restoration of water supply lines totally damaged by nature’s fury with lakhs of Capital Complex residents running from pillar to post daily for few buckets of water.

The work to build a spar and a bandh on Poma River near a huge rock begun today to be used as a passage. The river had changed its course completely eroding the road to the water source three-km ahead.

PHED CE Toko Jyoti, who has been constantly monitoring the ongoing works, told this daily that drilling and blasting the huge rock was impossible due to heavy downpour for which constructing a passage was the only alternative.  The passage once build would facilitate laying of 450-mm diameter pipes, staked along the road earlier, from the source to supply water to Itanagar, he said, adding hopefully the work would be completed as early as possible.

Itanagar with 1.2 lakh residents need 1.16 core litre water while Naharlagun and Nirjuli with 98,000 population need 70 lakh liters daily. But the people have been suffering after water supply lines were snapped on being damaged by torrential rains since one month.

PHED EE Tadar Mangku, AE Nabam Taga and JE Takam Tatak with men and machineries (folkland, JCB and piling instrument) begun works for an 1.2-metre diameter abutment with 20-metre deep base on Borum river at Naharlagun.

The alignment was measured by a Takam-led team on other side of the river before the sinking works resumed, while another group of labourers simultaneously begun rolling sausage wire to bind the boulders once the abutment is ready.

“The time needed for building an abutment depends on weather condition as heavy down pour could raise water level to affect the work”, Mangku said, adding “we might build one or two abutments”.