DC conducts eviction along Joram-Koloriang TAH stretch

ZIRO, Jul 13: An eviction drive was carried out on Tuesday along the Joram-Koloriang Highway to clear the hindrances from the point 20 km to 50 km of Package I & II of the Trans-Arunachal Highway (TAH).

Since the locals did not budge in spite of repeated reminders to clear the structures along the highway by the district administration as well as the construction agency, the massive eviction drive was initiated, reports DIPRO.

Deputy Commissioner Somcha Lowang along with ADC Toko Babu, EAC Highways Bamin Tarang and DLRSO Chakpu Raju monitored the entire eviction process as a result of which all the hindrances were settled.

Terming road connectivity as a catalyst to a vibrant economy, the DC said that the ongoing Covid-19 pandemic has not slowed the TAH construction works in Lower Subansiri district.

Highlighting the progress of the TAH stretches falling under Lower Sunbansiri, she said that a few hindrances under Package II in Tajgi area where eviction or dismantling was pending for 2-3 years have been cleared since May this year.

Currently 99 per cent of the hindrances along the Tajgi area under Package II have been cleared and 99 per cent of the compensation payments have been made.

She further said the pegging process in Yazali and Yachuli area has been completed and the eviction process is also expected to be completed soon in Yachuli area under the supervision of ADC Yachuli Toko Babu and CO Tashi Thongdok.

After taking over the charge as DC in May, Lowang has left no stones unturned to ensure the construction of the Highway is accelerated, the report added. (DIPRO)