By A O News Service

ITANAGAR, July 19: Many villages and towns of Siang, West Siang, Upper Siang and Shi-Yomi districts were cut off when heavy rainfall washed away 30-metre of Trans-Arunachal Highway (TAH) and NH-13 at Lelek in Siang district.

Villagers on either side of a missing stretch of the TAH waited 15 days for the government to act but of no use. Thus, people of Pangin and Kebang circles and adjoining villages decided not to wait for state’s highway department to do the work. Pangin is the circle headquarters about 30-km downhill of the damaged TAH portion and Kebang about 20-km uphill.

“People of 10 villages near  the damaged portion got together to collect local materials and about 50-60 volunteers took turns to buld the suspension bridge with bamboo, ropes and aluminium wires over seven days,” Lelek Bridge Construction Committee (LBCC) chairman Tagum Sitang said on Monday.

They took turns for a week thereafter to build a ropeway across the gap and reconnect parts of four districts, two of which border Tibet. The power department provided high-tension wires to be used temporarily for the suspension bridge that was completed on Sunday. The bridge now connects four strategic districts after 22 days.

The “temporary” period, villages said, could stretch to six months because of rain and soggy conditions and the repairing is unlikely to take place soon.

“For 21 days, people were forced to climb a steep 50-metre rocky mound near the damaged portion to bring in essentials or carry patients to the only major hospital at Pasighat (headquarters of East Siang district about 36-km away). Scaling and descending from the mound take two hours,” Sitang said, adding “Vehicles are now coming to the nearest point of damaged portion on either side for people to cross over and goods to be transshipped.”

Pasighat highway division EE Dabe Perme said they have started work on an alternative road skirting the damaged TAH portion that runs more than 2,400-km from Tawang in northwest Arunachal Pradesh to Wakro in the southeast.

“The alignment of the proposed alternative road entails working on 8-km, of which 4.5-km already exists. Earth-cutting is required for 3.5-km. We are through with 2.6-km and hope to provide a usable alternative road within 15-20 days,” he said.

The alternative road will connect Rottung, about 5-km uphill of the damaged portion.

The LBCC on Sunday submitted a memorandum to Chief Minister Pema Khandu seeking prompt restoration of strategic highways since the armed forces need to move to and from posts and bases along the India-Tibet border.

“The Centre recognises Arunachal Pradesh important from security point of view. It should ensure that the roads in the state are weather-proof and aligned according to the contours of the hills to be less vulnerable to damage besides affecting the local ecology the least,” Sitang added. (With feedback from Pintu Singh)