DC inspects progress of PMGSY road

PANGING, Aug 04: Siang DC Atul Tayeng Wednesday along with a team from district level monitoring committee, inspected the construction of a Pradhan Mantri Gram Sadak Yojana (PMGSY) road from Pangkeng to Bingung villages.

He was accompanied by District Programme Officer (DPO) and EE, AE, JE of RWD (Kaying Division), and the site engineer.

Enroute, the DC also made a stop at Bingung village to meet with the HGB, GBs and community members to discuss a land dispute over road construction. The matter was resolved amicably amongst all parties.

The DC stressed on reaching solutions that benefit the community, reports DIPRO.

The PMGSY road covers 24.72 kms for which form cutting is complete. Gravel sub-base (GSB) is completed for a 14 kms stretch. The DPO and EE RWD (Kaying) informed that 2 culverts of 6m span, 2 culverts of 4m span, and 13 culverts of 1.5m span have also been completed. Water Borne Mechanism-III (WBM-III) for a 1.15 km stretch and 765m of cement concrete (CC) drain has also been completed.

The DC highlighted the need for engineers across departments to be in constant communication as they work for a common goal. The DLMC discussed plans to visit other projects within the district accompanied by engineers from all departments concerned so as to ensure speedy and quality work, the report added.