PHED targets Aug 15 to solve Capital Complex water crisis

The water supply trial has to begin few days before to achieve August 15 target, said CE Jyoti

* PHED deserves praises: CS i/c

By A O News Service

ITANAGAR | Jul 27 | Capital Complex facing severe water since July 9 last after the water supply pipe lines were completely damaged and washed away by nature’s fury is likely to be solved by August 15 next.

The PHED has set August 15 as its target to resolve the crisis, chief secretary I/C Satya Gopal informed this daily in an exclusive interview immediately after inspecting Mopung-Mekha and Poma river confluence with PHED commissioner H K Shala, Capital DC Prince Dhawan and other officials. The PHED after taming the river has built a spur and bund for laying 450-mm diameter pipe line to facilitate flow of water from Mekha source, 3-km ahead.

“Travelling along the 9-km non-motorable road from Poma village on a Scorpio was highly risky. The vehicle was skidding at various muddy points while looking at the river valley below few hundred metres was sending shivers down the spine,” he recalled his personal experience.

However, he was happy to learn that Mekha river is known for its medicinal value of its water as the locals since time immemorial used to take bath in that river for getting cured from skin diseases.

PHED CE (WZ) Toko Jyoti and EE Tadar Mangku, who accompanied the team, explained the challenges before the department and the problems confronting the workers.

On learning that about 70 PHED workers and two JEs were living together in a make shift camp working  hard while Mangku supervising intermittently, Gopal  was shocked and said that people working against all odds deserve appreciation.

Emergency meeting decides steps to prevent

water-borne diseases, ensure water supply

Meanwhile, an emergency meeting, chaired by chief secretary Shakuntala D. Gamlin here on Wednesday, discussed prevailing acute water crisis in Capital Complex, and  decided war-footing measures to mitigate mass sufferings.

After PH&WS commissioner H K Shalla informed the damages in details adding the restoration works would take about six to nine months, even longer  to bring normalcy, an official release said.

Thus, to ensure potable water supply to prevent any outbreak of water borne diseases immediate actions approved included: Provision of safe drinking water, particularly to TRIHMS & RKMH, heliport, railway station, secretariat, Raj Bhawan, Niti Vihar and all vital installations including educational institutions; water should be supplied by tankers with clean syntax; a control room with a TRIAGE Centre with adequate stock of medicines and ORS would be activated for monitoring and managing all diarrheal and dysentery cases in both hospitals; prevention of mosquito breeding causing Dengue fever by taking adequate steps.

However, the CS  stressed on alternate back-ups to ensure uninterrupted water supply even during every monsoon and directed the PH&WS department to explore the possibility of constructing pipelines underneath the river-beds to avoid over ground damages by consulting experts while rain water harvesting system should  be introduced in all building plans in Capital Complex.

Principal home secretary Satya Gopal,  commissioners Hage Kojeen (education) & Kaling Tayeng (health &FW), Capital DC Prince Dhawan and state epidemiologist  Dr. L Jampa attended the meeting.

Meanwhile, DC Dhawan, addressing a awareness-cum-sensitization programme on vector borne diseases today, almost similar preventive measures were decided.

The meeting was attended by IMC chief councillor  Kipa Kaku, deputy chief councillor Tarh Nachung, councilors, CMEO Habung Lampung, DMO Dr. Tasso Khampu and other officers.(DIPRO)

Meanwhile, the APCC today flayed the GoAP over the prevailing severe water crisis and surface communication confronting the Capital Complex, particularly for lack of concrete plans and alternatives to end  mass suffer from the twin problems.

Hospitals, schools and colleges have been getting unfiltered muddy water due to failure of water treatment plant which may lead to outbreak of water borne diseases, an APCC release said and claimed that some severely affected people have been buying water from private suppliers though it is the responsibility of the GoAP to provide tankers to supply free water in affected areas.

Though there are areas not connected to urban centres and without pipeline, but the GoAP  has turned a mute spectator ,it said and demanded immediate improvement in water supply and road restoration, which have been smacking solution.

The Khandu led Govt. should have paid attention to procuring water tankers,  installing tube wells  in different locations, replaced old pumps and motors in water plants to mitigate the crisis.

PM Modi during his visit to the state had talked high about making Itanagar a ‘modern capital’ and Arunachal a ‘modern state’ which have turned out to cheap political promises to beg votes. Moreover, constant power cuts, fake recruitment rackets and other poor public utilities exposed Modi’s and hidden agenda of the BJP Govt. while locking horns with the public on all pro-public issue.