Underpass under focus for missing target: CE

ITANAGAR, Aug 31:  Though the PWD (Highway) had targeted to complete Bank Tinali underpass by August 31, but despite all possible efforts and focused attention, the works could not be completed due to constant rains and break down of batching plants of contractor M/s T.K. Engineering Consortium Pvt. Ltd. The balance works of underpass includes crash barrier, pavement and road furniture, according to PWD (Highway) chief engineer Sumnyak Sumnyan.

However, to maintain high quality construction and safety to road users/traffic, this work is being attended with utmost care and sincerity for completion at the earliest as and when window of good weather permits, he said in a release and lauded to public for their cooperation.

Meanwhile, MoRT&H has extended completion of four-lanning of NH-415 from Chandranagar to Papunallah under Package-A up till September 20 next, the release added.