BRO completes Sangam bridge over Shiyom

PANGING, Sept 01: Much to the relief of the commuters, a 320 feet bailey suspension bridge over Siyom river on Aalo-Boleng-Yingkiong road, has been completed by the Border Roads Organisation (BRO) and opened to traffic on Wednesday.

The PDC of the bridge was preponed by one month in view of prolonged road-blocks on two important axes leading to Aalo including, Likabali-Bame-Along and Pashighat-Pangin-Boleng.

The BRO faced extreme difficulty in launching the bridge due to heavy and unprecedented rainfall at the bridge construction site. The site engineers, however, were determined to make the bridge operational by the revised deadline given by their headquarters in Delhi.

BRO engineers worked in extended shifts from early morning till late in evening and completed the important bridge in record 35 days time.