PHED to begin water supply today

ITANAGAR | Aug 06 | When told its Sunday, Bhupen gave a wry smile. For him, and seventy others, all days were just work days that practically stretched into work nights every other day.

While citizens of the state capital poured their angst over the public health engineering & water supply department through whatever means available – notably Facebook – hundred odd workers toiled day and night clearing debris, constructing embankments, aligning pipes far from the visibility of the civilized world, making the jungles of Rilloh their temporary home. Unlike their counterparts in the city, they had no issues of water scarcity. River Poma and River Mopung Mike wouldn’t let that happen.

The state capital would remember for long the July9, 2017. Incessant rains created havoc across the twin cities – blocking roads, washing away pavements and snapping the very sources of water supply. Two days of life without water was enough to trigger frustrations amongst the citizens that grew by the day.

With pressure mounting on the Govt, a team of PHED officials under direct supervision of CE Toko Jyoti and EE Tadar Mangku silently set out on a mission. The GoAP set them August 15 as the deadline to resume water supply to the state capital.

In all 71 workers headed by three JEs made the confluence of Poma and Mopung Mike rivers as their base camp and took the job at hand head on. Incidentally, the damage on the pipeline was severest at the place where they had set their camp. The Mopung Mike river had changed its course and washed away about 100 mtrs of DI pipes…never to be retrieved.

In 24 days and 24 half days (worked late till about 10-11 pm) they repaired, constructed, aligned and fixed at least 15 damaged portions.

As PHE&WS Minister Bamang Felix reached the campsite Sunday morning a jubilant PHED team informed that all the fixing have been completed and water is being released to the WTP.

Felix, who along with CE Jyoti and EE Mangku congratulated the workers and officials for their determination and completing the job ahead of the deadline. Felix wished the workers and announced that all will be given overtime payment after completion of the entire project.

With water reaching the WTP it would be a matter of few hours before Itanagar heaves a sigh of relief. According to Mangku by Aug 7 afternoon water should be reaching people’s homes.

Felix also inspected the ongoing repair works of Naharlagun water supply near Borum and Yupia tri-junction. About 3-km of new pipeline is being put in place that would take another couple of days.

Jyoti informed that Naharlagun water supply would be completely restored by August 11 next, thereby keeping a step ahead of the deadline.

Meanwhile, Bhupen and friends still have unfinished works. About 3-km of approach road up to the water intake point has to be restored.  It’s another three-four days for them in the jungle camp.