BRO blast off last portion to construct Sela Tunnel 

By Pradeep Kumar

ITANAGAR, Jan 22: Border Roads Organization (BRO) Director General  Lt Gen Rajeev Chaudhry conducted final breakthrough blast for 980m long tunnel 1 (T1) at 11.30 am on Saturday marking the completion of more than 4000m of cumulative excavation over the last two years.

He made the blast through an e-ceremony from New Delhi to culminate the excavation works of the complete project, BRO’s Vartak chief engineer (P) Col Ajay Bhandari told this daily.

Strategic Sela Pass, part of Trans-Arunachal Highway (NH-13) located at 13,800 feet altitude along Bhalukpong-Dirang-Tawang route in West Kameng district of Arunachal Pradesh, poses tough challenges for the commuters, particularly during winter due to heavy snowfall.

The Centre, therefore, had decided to build 3,000m Sela Tunnel to ensure all-weather connectivity to Tawang and entrusted the job to the BRO. Thus, its works had started in 2019 to connect with NH 13 by a new 12.4-km road to reduce 10-km distance between Dirang and Tawang by and travel time of one hour with a 3-year completion target by February 2022.

The T1 is a 980m long single tube tunnel and T2 a 1555m long twin tube tunnel. The T2 has one bi-lane tube for traffic and one escape tube for emergencies. It will also be one of the longest tunnels to have been built above 13000 feet altitude. The first tunnel cuts through a longitudinal ridge to join the second tunnel and runs through the main Sela-Chabrela ridge. The two tunnels together bypass the Sela Pass and maintain an elevation of 3000m.

Defence Minister Rajnath Singh had initiated the final breakthrough blast for T2 (1555 metres) from New Delhi on 14 Oct 2021.

This important project once complete would serve as the lifeline for Tawang located along Indo-China border not only for civilians but also for defence forces.

The foundation stone of the project was virtually laid by Prime Minister Narendra Modi in 2019 and excavation work on T1 had started with the blast triggered by DG Chaudhry on January 15, 2021. It was followed by a virtual blast triggered by Defence Minister Singh on October 14, 2021 from India Gate to mark the end of excavation of T2, Col Bhandari informed.

The challenging project includes construction of a 7-km approach road to T1, which takes off from Baliapara-Charduar-Tawang (BCT) road and a 1.3-km link road to connect Tl with T2.

The BRO over the last two years has been consistently achieving success in execution of infrastructures with marvels in most challenging areas of the nation. It created  two world records by building 9.02-km Atal Tunnel or Rohtang Tunnel built under the Rohtang Pass in eastern Pir Panjal range of the Himalayas on Leh-Manali Highway in Himachal Pradesh, the longest highway single-tube tunnel above 10,000 feet in the world and dedicated to the nation on 03 Oct 2020 and 52-km motorable road that connects remote villages in eastern Ladakh and traverses the 19,023-feet hig Umling La Pass. Built at a cost of Rs 3,200 crore to make it the highest motorable pass in the world and dedicated to the nation on  Nov 16, 2021.

The BRO has also taken up tunnelling in a big way with successful completion of high altitude and mountainous tunnels, in addition to Atal Tunnel, Rohtang in Himachal Pradesh, Chamba Tunnel in Uttarakhand toeing its motto “Shramena Sarvam Sadhyam (everything is achievable through hardwork)”.