First passenger flight to land at Hollongi on August 15

  • Guv, CM inspects construction work of Greenfield Airport

ITANAGAR, Mar 08: The Greenfield Airport at Hollongi here, the first full-fledged airport of the state, is all set to get operationalised on Independence Day this year, well ahead of its November 2022 scheduled date of completion.

Developed by the Airports Authority of India (AAI) with an estimated cost of Rs 645 crores, it is designed to be a Greenfield Airport with eight check-in counters and can accommodate 200 passengers during peak hours of the day.

Hollongi is about 15 kilometers from the state capital Itanagar.

State Governor Brig (Retd) Dr B D Mishra and Chief Minister Pema Khandu on Tuesday reviewed the progress of the construction of the airport along with state Civil Aviation Minister Nakap Nalo, Rajya Sabha MP Nabam Rebia, local MLA Tana Hali Tara and Chief Secretary Naresh Kumar besides senior officials of the AAI.

Khandu during the joint inspection, announced that preparations are in place to receive the first ever passenger flight on 15 August next at the airport.

Both Governor and the Chief Minister took a detailed review of all aspects of the airport from representatives of the Airport Authority of India (AAI), Power Grid Corporation of India (PGCIL), state government agencies like PWD, PHED and Power and all contractors involved in the project.

Both insisted that the airport has to be made operational by 15 August, to which end each and every stakeholder has to plan and work accordingly.

To a question by the Governor ‘can you do it or not’ everybody said ‘yes’.

Appreciating all involved in the project, Khandu said this must be the only greenfield airport in the country, work on which started from scrap and would be made operational in record time.

“This in fact is a national project and you must all feel proud and privileged to be involved in it and on the way to create history,” he said.

Khandu reminded all of their commitment to finish all jobs required to make the airport operational and said, “I put my faith on you all that you will stand by your commitment no matter what.”

Meanwhile, the Governor offered to intervene wherever any bottleneck is beyond resolution by any stakeholder. He assured he will use his good office and personally speak to any authority, private or government, to resolve any shortage or official clearance so that the deadline is met.

He also asked the local legislator Tana Hali, who was present in the review meeting, to coordinate with the deputy commissioner and resolve all local issues immediately. To the Chief Secretary and Secretary Civil Aviation, Brig Mishra said that all requisite clearances have to be procured well in advance.

“Let us all put our heads and shoulders together to make this dream of August 15, this year, come true,” he said.

The governor stressed that every component builders should realize the pressing need, the urgency and the necessity to finish the project at the earliest.

He advised the project managers and officials for weekly reporting and monitoring for all components of the airport and to take immediate actions to expedite the progress of the work.

The governor exhorted the officials to work with the spirit of ‘we will do it’ and accomplish their mission.

Bulk water supply system to the airport is almost complete while the approach road would be complete by March end, assured implementing agency PWD.

The PGCIL assured that the portion of the 132 KV Power Grid line would be diverted before time as work is under progress at double the speed. Buildings for medical unit, power and fire stations are also almost complete.

In short, all the works required to make the airport operational will be completed by mid-June.

Both Khandu and Mishra reminded all that they will be reviewing the progress on a day-to-day basis besides visiting personally whenever needed.

State Civil Aviation Minister Nakap Nalo, MP Nabam Rebia, legislator Tana Hali, Chief Secretary Naresh Kumar, Secretary Civil Aviation Swapnil M Naik and officials of civil aviation, work departments, state police, district administration and others were present in the review meeting held at the site conference hall of the AAI.

The chief secretary and AAI regional executive director Ravi Kant briefed the governor and the chief minister about the status, progress and timeline of the works completion, while state civil aviation secretary Swapnil M Naik informed about the progress of peripheral works.

State Security Advisor Major General S C Mohanty gave details of the security requirements, including the manpower selection, their training, their affiliation for job familiarization and the security personnel’s availability.

Earlier, the governor and the chief minister inspected the ongoing works of the critical structures, runway works, Kokila River diversion measures.

According to official sources, the airport will be available for operations of A-321 category aircraft. The airport will also get its runway extended by 500 m to accommodate A-321 type of aircraft in the future.

With an area of 4100 sqm, the airport is going to be equipped with all modern facilities for passengers.

More that 80 percent of the airside work is already complete. The terminal will be an energy efficient building with Rain Water Harvesting System and sustainable landscape. The airport will also have a medical centre, fire station, among other things, the sources added.