Execute schemes on time: Kundra

ITANAGAR | Aug 17 | Power & finance commissioner Ashish Kundra today advocated timely completion of scheme as PMO has been monitoring through specific App regularly.

Addressing a meeting to review developmental projects undertaken by power department, he directed  to ensure early settlement of legal litigation against some of districts which have majority of un-electrified villages.

On Power Minister Tamiyo Taga’s query about list of un-electrified villages and their selection, he clarified that there were some un-electrified villages missing from the list which were to be included in the scheme. Thus, the GoI has agreed to consider these missing villages through contractors who were awarded the works of nearest village(s) through on grid or off grid.

Power Development Corp Ltd representatives highlighted details of projects undertaken through off grid means in which stand alone solar roof tops are to be provided.

All materials will be reaching respective main warehouses and sites by September,  as per the execution plan, as inspections have been completed.  He sought appointment of a nodal officer from APEDA for better liasioning and early project execution.

SE Rubu Tago gave a highlighted on power development scheme (IPDS) to strengthen sub-transmission, distribution system and metering. The project has been awarded recently after rejecting pleas of the aggrieved party by the high court, he said.

The meeting attended by power department engineers including CE (transmission) Anong Perme, CE (EEZ) O Moyong, CE (CEZ) T Mara, APEDA director M Loya, was conducted as GoI team headed by power secretary is expected to visit the state in last part of August.

SE (transmission) HR Bado, gave presentation on PGCIL scheme involving transmission lines of 33KV, 132KV and above capacity with associated substations, when it came to limelight that some substations are yet to be finalised and overall progress was only 25% while Mara stressed on electrical inspectorate to ensure quality and specifications of the machineries and equipments. DDUGJY nodal officer G Lingi enlisted details of DDUGJY schemes which target all un-electrified villages to be electrified by December. The power department is executing these projects on grid projects and APEDA through PDCL for off grid projects.

Kundra called for meaningful dialogue with the GoI for a tripartite agreement involving the GoAP in  MOA for having legality on our part after taking over the projects on its completion.