BRO relaunches swept Bailey bridge swiftly to evoke kudos

  • Challenging task accomplished in record time: CE

By Pradeep Kumar

NAHARLAGUN, July 12: The Bailey bridge on Koloriang-Lee-Huri road in Kurung Kumey district, about 1-km from Lee, washed away by huge boulders triggered by a major flash flood on July 3 last, was re-launched under extremely challenging conditions by Border Roads Organization (BRO)’s Project Arunanak on Sunday last.

Project Arunanak chief engineer Anirudh S Kanwar, while talking to this daily here on Tuesday, said that it was a very challenging task posed by tough circumstances including incessant rains and landslides for which innovative techniques were used to overcome all challenges.

The 119 Road Construction Company (RCC)/756 BRTF team under officer commanding EE (civil) Roshan and platoon commander Maj Mohit leveled the river bed to temporarily divert the traffic on July 4 to facilitate smooth works.

They worked round the clock for seven days despite heavy rains to restore connectivity by launching the bridge, the CE said, adding it took two days to clear five massive landslide points and making a temporary crossing over a washed away culvert with heavy flow of slush for transporting required men, machines and bridging stores to the spot.

However, there was limited space to unload the materials, assemble and launch the bridge. Thus, loaded vehicles had to move 1-km in reverse gear to dump stores on site, innovative method of using a 20-ton excavator used as counter weight of the bridge  to overcome limited backspace, he informed.

The team of 1079 field workshop pitched in with heavy lifting, fabrication and welding support at the site to speed up works. A major landslide occurred at the site but few men on work escaped narrowly with serious injuries, he said.

The bridge had to be launched oblique to the centre line due to space constraints for realigning later, but due to space constraints and abutment damaged by river current, the bridge span had to be increased from 60-ft to 80-ft and again  to 100 ft during construction, he said, adding the entire team with tremendous grit, determination and professionalism worked undeterred to accomplish their assigned mission.

The bridge being lifeline brought the much desired relief to people living in remote villages of Damin, Huri and beyond as well as defence forces heading to Indo-China border, said former Kurung Kumey ZPC Sangha Tagik

The BRO deserves kudos for speedy re-launching of the bridge under challenging situations, he said and urged them to come to the rescue of border villagers when such situations occur in future, he added.

EAC Ocean Gao also lauded the BRO, particularly 119 RCC, for restoring the lifeline of the area in a very short time.

In fact, BRO ADG (North East) P H K Singh, on being apprised about re-launching of the bridge by the CE on Monday, had lauded all engineers and men involved for their dedicated services.