AALO | Mar 09 | All 12 power developer companies have suspended their works in West Siang district, DC Gamli Padu disclosed during a review meeting on Wednesday.
It has been decided to start hydro-electrical projects (HEPs) in Mechuka sub-division, issue notices to defaulters and restore Sirutali and Liromoba HEP power stations fully to boost power scenario, he said, and directed to test generating capacity of Liromoba HEP by providing 1-mw to Aalo and 350-kw to Tirbin on test basis by March 15.
It was disclosed by the engineers that Liromoba HEP station has been generating only 220-330 KW now against installed capacity of 2000kw due to transmission network snag, engineers said, adding two units of Siru Tali HEP station was ready for generation on grid mode but transmission lines were poising problems.
A committee headed by Yomcha ADC with Kamba, Tirbin, Kaying and hydropower AEs as members was formed to assess functioning of HEP stations. The review covered revenue leakages in Govt institution, power theft and proper metering in private residences, institutions, Govt. establishments.
Progress of ongoing double lane Aalo-Bam and Aalo-Mechuka stretches of Trans-Arunachal Highway was reviewed covering law and order problem by DC Gamli Padu in a meeting with BRTF, TK, JKM and KCL(JV) here on Wednesday.
Padu said that The road has been handed over to Ministry of Highway on November 13 last and almost all utilities have been shifted for easy works to facilitate smooth riding.
Responding to the DC’s queries, the concessionaire and BRTF informed that there was no major issues barring a few local problems being settled locally. (DIPRO)