BRO inks record to complete defence road to China border

 

ITANAGAR | Sep 04 | A 14-year-old 71.3-km Sarli-Huri road in  Kurung Kumey district, a defence road, leading to China border, has been completed by Project Arunank of Border Roads Organisation (BRO).

The project was taken up by 85 RCC/756 BRTF of Project Arunank  in May 2006 relentless efforts braving inhospitable terrain achieved the success that linked  Pipa, Damin, Huri and other remote villages. This would facilitate movement of defence forces for national security and boost socio-economic development of villagers, BRO sources told this daily.

Air Force helicopters airlifted heavy construction plant and machinery under slung after  dismantling them to number of parts from  Ziro to Damin. They were reassembled at the remote base before pressing into service.

A new road from Huri-Taliha in Upper Subansiri district and a new 155-km  green field alignment were also completed recently.

​As directed by Defence Ministry last year to expedite work progress, Project Arunank marched forward from Ziro to Jeevan, ahead of Koloriang in April last. Three additional dozers were dismantled at Ziro, and inducted by air to 44-km base where they were reassembled.

These efforts facilitated earth cutting of 10-km road in a year which is an unprecedented achievement, the source said, adding the achievement justified BRO’s motto “Creates, Connects, and Cares”, particularly in border and hilly states like  Arunachal Pradesh.