Hurdles cleared for double-land road construction in Anjaw

Our Correspondent

TEZU, Nov 22: Anjaw the remotest district of the state, is all set to get a infrastructure boost with coming up of high class double lane road to connect all border area, which remained unattended since long due to land compensation issues.

With clearance of fund from the district administration, the work on the road would start soon by the National Highway Infrastructure Development Corporation Limited (NHIDCL).

“Land compensation issue had halted the construction work for five to six,” rued a denizen of the district.

The much-hyped highway remained in a deadlock due to non-clearance of compensation by the land owners. Initially, they claimed Rs 82 crore as compensation which was found illogical and the administration re-surveyed for several occasions. Later, the Centre had agreed to pay an amount of Rs 45 crore as compensation thereby putting an end to the stalemate.

“Three former DCs including, Mamta Riba, Dagbom Riba and Ayushi Sudan, made relentless efforts to acquire land for the project but in vain. The compensation issue was in the court but this time the Ministry of Road Transport & Highway (MoRTH) fixed the compensation amount and finalized to expedite the pace of construction work,” Hayuliang MLA Dasanglu Pul said.

The BJP government has given top priority to connect remote border districts with double lane highway for hassle free movement of Armed forces and civilians besides, promoting tourism and for socio-economic development, she added.

Formation work with 20 culverts has been completed in a stretch of 10.5 kilometers road between Arrowa to Khupa along the 23 km long highway. There are a total of 120 culverts in the entire stretch of the road.

“We have completed land acquisition for a certain stretch of the highway while others are yet to be acquired. The district administration should clear the rest of the road to speed up the work before the monsoon,” an official of the NHIDCL said.