AALO, Apr 05: Sports & Youth Affairs Minister Mama Natung Wednesday convened a review meeting here, to discuss the long pending sports outdoor stadium.
The minister inspected the outdoor stadium and later convened the review meeting on the progress and other issues related to the outdoor stadium.
District Sports Officer Tumto Loyi highlighted the progress of the ongoing project.
The construction of the stadium at Aalo which started in 2016, was discontinued for two years due to the Covid 19 pandemic.
As per project Manager of T K Engineering & Consotorium, 68 per cent physical work of the stadium has been completed.
During the visit of Chief Minister Pema Khandu in November last year, the construction agency assured to complete the ongoing project within March this year. However, it could not be completed due to various reasons.
Natung has directed the executing agency to increase the labour force and should work 24×7 in order to complete the project by October this year.
He added that there is no objection from the local people and there is also no dearth of funds for the project.
The minister urged the DC and the district sports department to physically monitor the work.
West Siang DC Penga Tato assured the minister of logistic support from the district administration in early completion of the project.
Sports & Youth Affairs secretary Anurudin Singh discussed with the implementing agencies and appealed to them to complete the work as desired by the minister. (DIPRO)