BOLENG, Apr 13: The Subbung 2×1500 kw small hydro project near Supsing village in Siang district has been put back into commercial operation from Thursday after restoration of flood damaged structures.
The plant was under shutdown since August 2021 after extensive damages of water conducting system due to heavy flood and landslides caused by Subbung Stream (Nallah).
Subbung is a tributary of Simang River.
According to hydropower development department sources, the plant will supply electricity to Boleng Town and it’s adjoining villages like Yingku, Yibuk, Sine, Supsing, Suple, Pareng, Dosing, Rengo, Lileng, Parong etc.
Earlier, an alternative power supply was provided through Yembung micro hydel of Kebang Village.