By Our Staff Reporter
ITANAAGAR | Sept 23 | The 2642-km long Trans-Arunachal Highway roads is being built under 72 packages, of which the PWD will execute 465-km , NHIDCL – 870-km, BRO-597-km, Union Mo RTH-710-km. However, only 696-km has built due to slow progress. Few project of which Forest clearance of Akajan-Bame, Joram-Koloriang, Nichpu-Hoj projects are awaited though under active consideration.
These facts surfaced during the 8th highway monitoring committee (HMC) meeting including review of flagship programme of CM and PM package ongoing NH construction here today.
I/c chief secretary Ashis Kundra said that all issues related to highway construction involved royalty, environment clearance, updated execution status, fund release and disbursement of compensation and court cases besides issues relating to power transmission and PHED.
Follow up action of 7th HMC minutes was reviewed on 08.04.17 last and directed all officers to take up all flagship programme sincerely. He requested the DCs to discuses and initiate steps with district level committee for speedy execution and directed Capital district administration and PHE & power deptt officials to take up shifting of all utilities in Capital Complex to facilitate four-lane NH construction.
PWD commissioner Belati Pertin said that district administration should deal with all issues and liaison to resolve unresolved issues to speed up progress.
He said that because of Incessant rain had caused huge destruction of roads while restoration has been committed. However, total estimate of Rs 129 crore loss has been submitted so far but spent without receiving funds and expect the MoRTH should have Corpus fund for such eventuality.
CE (highway) Toli Basar said that several direction have been issued from time to time. Most of the projects are under execution, few are yet to start as the official and other formalities are underway. Some project have been dragged to court for various reasons, but steps are taken for to redress all issues including court case.
Papum Pare, Kurung Kumey, Longding, Upper Subansiri DCs, Arunank, Bartak, Udayak, Brahamank, PWD(CZ), RWD (EZ) CES, district LRSOs, HoDS, MoRTH Guwahati & Tezpur regional offices, officials of NHIDCL, environment & forest, BSNL, police, power, PHED and executing agencies were present.