Namsai water supply not gravity driven, but lift water system: DC

NAMSAI, Sept 26:  Namsai MLA Chau Zingnu Namchoom, addressing District Water & Sanitation Mission (DWSM) meeting, chaired by DC-cum-DWSM chairman C.R Khampa here on Tuesday, urged member-secretaries to conduct periodic block level coordination meeting to take stock of ground issues, prioritize them and bring to notice of DWSM.

Multi-departmental convergence & effective IEC have a big role to play for saturation of JJM and SBM; he said and called for site visits by member-secretaries along with PHED engineers. He suggested members of households facing water crisis should be included in village water and sanitation committee (VWSC) to create a sense of responsibility.

The exposure visits of VWSC members should be planned to understand VWSC function and success of water treatment plants. The issues and hurdles of the department shall be placed at state level forum, Namchoom added.

Majority of completed projects under JJM in Lekang circle are defunct, Lekang MLA Jummum Ete Deori said, adding “There is lack of coordination and awareness among villagers which calls for our intervention”. Hence a strategy should be worked out to make all JJM projects functional, she said. The list of all works executed by various departments should be given to legislators and ZPMs concerned for monitoring, she added.

The DC, in his presidential address, said that DWSM is activity carried out by the PHWS&ED as part of Jal Jeevan Mission. Unlike other parts of the state,   district’s water supply system is not gravity driven, but mostly regulated through lift water system, he said, adding that sustaining water supply has become a big concern for which village-wise VWSC has been formed but the sense of ownership is lacking.

Thus, despite achieving 90% plus physical achievement, many projects are defunct, he said and suggested panchayats to have village level  functional office and urged member-secretaries to make gram panchayat offices functional.

DPDO W. Mossang informed that under the grey water management for achieving ODF plus, work is being done in convergence with RD department. Total 605 unit individual soak pits and drains are being built under MGNREGA with an aim to achieve 100% saturation by October next. (DIPRO)