YOMCHA | Oct 09 | S&T department tam led by APS&T chairman Bamang Mangha inspected department’s on-going projects in West Siang district on Sunday.
During inspection to the 100 KW mini and micro hydel project at Sirorijo under Yomcha circle, the team fond the work progress slow and directed the executing agency to speed up progress to complete it before March 2018.
Later, the team visited Rikpu Ronya & Doko Putu village and inspected completed scheme of improvement of traditional water mill which generate 3 KW of power and powers rice mill. The team also visited water mill and multi layers agro forestry scheme and interacted with villagers and GPMs.
While interacting with Doko Putu villagers, Mangha said that the GoAP projects should be beneficial to the people. The traditional water mill is not covering larger area but he urged the contractor and local residents to maintain it in self interest.
The Sirorijo was a pilot project of the GoI and once successful would be recommended to the Centre for more such projects, Mangha said, before team visited the forestry scheme, taken up in Jartar Ronya’s private land at Doko Putu. Different schemes of economic sustainability, like fish, agri-horti culture and tree plantation would be taken up for which water would be fed from perennial Koe Krow, Kome & Mobiang Kojak sources.
Responding to a memorandum submitted by locals seeking restoration of damaged power channel of Dori-2X100 KW at Doku Potu, Mangha directed project incharge to restore soon, urged the department to provide an operator for traditional water mill and MH project and agreed to look into other matters.
Chief Engineer-cum-disaster management chairman Tanya Ronya, HGB Lidam Ronya and GSU president Binya Ronya Among, besides officers, accompanied the team including joint directors Dr. Debajit Mahanta, Liagi Tajo (remote sensing), among others.