- ‘Future Power House of India’ to be a reality!
ITANAGAR, Sept 03: Chief Minister Pema Khandu during 6th steering committee meeting (SCM) here on Tuesday reviewed the status of hydropower projects in Arunachal Pradesh focusing on forest clearance, techno-economic clearance, land acquisition and environmental clearance.
The all-important SCM, attended by top Govt officials and heads of CPSUs – NHPC Ltd, SJVN Ltd, NEEPCO, and THDC India Ltd and Union joint secretary (Hydro) Mohammad Afzal, especially focused on the 13 hydropower projects in the state allotted to these PSUs with a combined investment estimated to exceed Rs one lakh crore.
Stressing on significance of hydropower development for state’s growth in fields of economy, employment and industrialization, Khandu urged all stakeholders to jointly and earnestly work to clear all hurdles hampering smooth progress in execution of the 13 said projects.
“I direct all departments concerned and DCs to ensure that there are no delays from the state government in expediting the necessary tasks required for clearances. Hydropower is vital for our state’s revenue, employment, and economic opportunities. We must ensure that all projects move forward swiftly and efficiently,” he said.
Recalling the Union Cabinet’s approval for providing central financial assistance (CFA) to the Govts of North Eastern Region (NER) towards their equity participation for development of hydro electric projects in the NER through joint venture collaboration between state entities and CPSUs last week, its delay is the biggest stakeholder for his state, Khandu said.
He informed that the Union Cabinet decision is a result of the state’s persistent requests and would benefit the state the most given its huge hydropower potential.
The Centre’s decision has an outlay of Rs. 4,136 crore to be implemented from FY 2024-25 to FY 2031-32. A cumulative hydro capacity of about 15000-MW would be supported under the proposal. The projects would be funded through 10% gross budgetary support for NER from total outlay of Union Ministry of Power, according to an official release.
On 12.08.23, the MoAs were signed between NHPCL and the GoAP to develop 2000-MW Subansiri Upper Hydroelectric Project and 1800-MW Kamala Hydroelectric Project, the NHPCL said in a release.
AONS adds: This Himalayan state with hydropower potentials of around 58,000-MW has earned the sobriquet “Future Power House of India, for which becomes the centre of discussion when any union minister visits the state.
On September 1, Governor Lt. General (Retd) K T Parnaik had told Union MoS for Heavy Industries and Steel Bhupathi Raju Srinivasa Varma that only a small portion has been harnessed so far, while, some sections are also opposing proposed mega dams.
The 405-MW Ranganadi Project (renamed as Panyor Lower HEP) was the first major hydroelectric project in Lower Subansiri district, whose execution works had started in 1988 and the project was commissioned in 2002.
The process has almost taken pause since then and state capital of ‘power house of the country’ faces power cuts very often than not. CM Khandu known for his commitment to development, hopefully speed up commissioning of these 13 HEPs to turn the sobriquet into a reality.