By Manoj Singh
ITANAGAR, Nov 04: Itanagar Permanent Bench of Gauhati High Court has given two-month time to the PWD Highway for complete maintenance of Papu Nallah-Nirjuli stretch of NH-415 under Package-B, Itanagar Capital Complex DC Toko Babu told media persons on Monday afternoon.
The HC had directed the executing agency PWD(Highway) earlier, but it failed to do so. Thus, the HC on October 31 directed again for proper maintenance of the said stretch, he said, adding after the HC direction, he had spokento PWD(H) engineers, who confirmed that maintenance of the stretch has begun.
The PWD (H) has entrusted the work to a new firm as previous contractor (Woodhill Shivam) had failed, he said.
The HC earlier had given 60-day time to then contractor M/s Tama Fabrication to complete the maintenance work and asked the department to file a status report by December 3, he said, adding the matter has to be listed for hearing on December 5 next.
Moreover, the HC has also directed to constructflyover in tune with terms of the agreement. The date of completion has been extended till July 2026, he disclosed.
A division bench had passed the order while hearing PIL No 11/2024 filed in July 2024, in which senior advocate Dicky Panging had appeared as counsel for the petitioners, he said.
“The slow pace of construction under Package B, which starts from Papu Nallah and ends at Nirjuli, has been causing immense inconvenience to Itanagar Capital Region people. Despite several assurances from the GoAP, the work continues at a snail’s pace. I am equally worried about the work progress.
“I am not sure that the agency will be able to compete the main work of constructing flyover on time as per given date. Thus, administrative officers have been inspecting repeatedly”, the DC added.