PANGGO, Nov 15: The 82-km Panggo–Jorging Defence Road, being executed by NHIDCL through an EPC contractor, aims to provide vital last-mile connectivity to Tango-1 & Tango-2 Army and ITBP BOPs along Indo-China border, was inspected by Upper Siang DC Talo Jerang on Saturday.
The work on this strategically important project begun on January 26, the contractor did 15.5-km formation cutting, constructed breast walls and retaining walls at multiple locations and in 10 months, an exceptional feat considering the challenging hilly terrain.
Jerang, during inspection, interacted with project engineers and lauded satisfactory progress made so far. He instructed them to strictly maintain quality at every stage, including sub-grade preparation, GSB, WMM, DBM, and BC works.
The completion of this road will significantly enhance strategic mobility and improve accessibility to remote border areas, the DC emphatically said. (DIPRO)