The two-day trip of Chief Minister Pema Khandu along with Deputy Chief Minister Chowna Mein, Ministers Ojing Tasing and Nyato Dukam, Advisors to Chief Minister Ninong Ering and Alo Libang and senior officials to Boleng and Yingkiong, headquarters of Siang and Upper Siang districts,  to interact with the public, particularly those to be affected by proposed 11,000-MW Siang Upper Multipurpose Project (SUMP) on Siang River did not yield desired result as people, mostly  indigenous women and farmers, holding banners inscribed with “No Survey, No Dam”, were agitating.

The CM on first day of his two-day visit to the area, while interacting with stakeholders at Boleng on Tuesday had categorically said that the Govt was not forcing anyone to cooperate in executing the project. But the PFR survey would help to take an informed decision whether to execute the project or not.

Tensions over the proposed SUMP) intensified in Upper Siang district after villagers clashed with security personnel in Geku on September 28, amid continued opposition to the project and the deployment of Central Armed Police Force (CAPF) personnel for the preliminary feasibilityrReport (PFR) survey.

According to reports, protesters took to the streets opposing both the proposed project and the presence of security personnel in the area. The situation turned tense after Govt vehicles were reportedly damaged, following which security forces intervened. Four people were arrested in connection with the incident, while security was   strengthened in the area.

China is building the world’s largest hydroelectric dam in lower parts of Yarlung Tsangpo River in Tibet, about 50-km from the border with India. Its construction continues unabetted despite concerns in India and Bangladesh over water supply and environmental impacts downstream.

Now, a Beijing-backed geological study has flagged its structural safety, the South China Morning Post reported.   An active fault line directly beneath the project could pose a threat to the mega dam and significantly affect the integrity of its infrastructure, according to the findings, published in a study supervised by the state-owned China Geological Survey, added.

The Paizhen Fault runs directly through the reservoir area of the massive hydropower project, the study, published last month in the Chinese-language journal Sedimentary Geology and Tethyan Geology, stated.

Researchers said the fault has remained active since the Pleistocene (Ice Age) and could significantly affect the structural integrity of dams, bridges, roads, tunnels and other infrastructure built in the region.

The Yarlung Tsangpo flows into India’s Arunachal Pradesh and Assam as the Brahmaputra River before entering Bangladesh as the Jamuna River. The team noted that the fault has fractured surrounding rocks and changed their mechanical properties, making the foundation bearing capacity and structural stability of nearby engineering projects more vulnerable to damage.

The terrain in the reservoir area has a loose structure and weak cohesion, warning that fault activity, earthquakes and prolonged immersion could easily trigger instability in the slopes on both sides of the reservoir, they added.

The Yarlung Tsangpo downstream hydropower project, construction of which began last year, is expected to generate around 300 billion kilowatt-hours of electricity annually, with a capacity nearly three times that of China’s Three Gorges Dam.

“Since the Pai village area is located within the construction zone of the Yarlung Tsangpo downstream hydropower project, its records of Quaternary tectonic activity provide an       important basis for exploring the structural stability of nearby projects,” the team said.

Researchers said geological records indicate that the Paizhen Fault remained active well into the Holocene period, with evidence showing movement as recently as about 9,500 years ago.   They also cited the magnitude 6.9 Milin earthquake that struck Tibet in 2017 near the northern end of the fault as evidence of the fault line’s modern seismic potential. According to the researchers, future earthquakes could trigger landslides and collapses that may endanger engineering structures and personnel.

The study was conducted by researchers from Chengdu University of Technology, the Civil-Military Integration Centre of the China Geological Survey, and the Middle Yarlung Zangbo River Natural Resources Observation and Research Station.

To reduce these risks, the study recommends strengthening structural stability during construction through measures such as slope reinforcement, retaining barriers to minimise the possibility of landslides and collapse.

All said and done, it is important to recall that on 11.06.2000, a dam collapse in Tibet had swelled Siang River and 30-feet high flood water had swept through Pasight town on the mid night when all were fast asleep.

It had devastated the centurion town and many people with the help of IAF helicopter were rescued from marooned areas by then SP Robin Hibu, present Delhi Police special commissioner, assisted by Bosiram Siram, present APCC president.  Beside large scale devastation of properties, six deaths were reported.

It is feared that China could use the dam as “waterbomb” and if it did so its consequences could be imagined. The SUMP has been proposed to neutralise the impacts of Medog Hydropower Station, a planned 60,000-MW run-of-the-river hydroelectric project on a single stretch or valley of a river under development. It is of four cascade dams across Yarlung Tsangpo River and five separate power stations on completion.