CE: Commercial operation of Aalo-Pasighat line soon

ITANAGAR | Mar 06 | Toping the GoAP thrust of 3Es (education, electricity & employment), the department of power is all set to operate the Aalo-Pasighat 77-km 132/33KV extra high voltage transmission line for commercial purposes soon.
Construction works of the said transmission line though completed on 05.01.17 but its final countdown for commercial operation begun today, DOP CE (TPM zone) Anong Perme said in a release.
The 33KV line was successfully charged and tested today while the test charging process at desired voltage of 132KV has begun paving the way for last mile check up of the systems besides other preparedness.
The mission will complete on receipts of all statutory clearances from electrical inspectors, the state load dispatch centre (SLDC) and RLDC for the commercial operation to boost power supply in its feeder areas, he added.