By Our Staff Reporter
ITANAGAR | Aug 26 | The new highway alignment for four-line in Capital Complex would damage four buildings (total 8 rooms) including P-Sector GS school HM and class rooms, councilor cum-school managing development committee (SMDA) member Gora Lotak claimed.
Strongly opposing the new alignment, he said that the final measurement of right of way (RoW) 15m from the centre of road was given by the NH authority and a structure toeing the measurement has been erected outside the school boundary wall. But it was utter surprising that the final measurement team of NH marked the sign inside the school wall. This new alignment will damage building comprising six class rooms including headmaster and SBSE room. The location is more than 30 meters from the centre of the road, he claimed, adding the latest GoAP decision on RoW has reportedly been 12 m for highway widening.
The Govt. school provides education to needy students of six feeder primary school and 4 upper primary schools, and total strength stood at 1100 students for current 2017-18 academic session.
The SMDC with parents & guardians had a meeting in this regards when all totally opposed new measurement, Lotak said, adding none was ready to surrender beyond 12 meter. Thus, a complaint was lodged with the DC urging to look into the matter. If the demand was not met, it has been decided to refund Rs 45 lakh compensation and take extreme step for the sake of the students.
“If compensation amount is the bone of contention that we will return the amount without second thought. We will resort to democratic process to protect school land,” Lotak added.
Condemning the new alignment, All Papum Pare District Student Union (APPDSU) vice president Tok Nanu dittoed Lotak’s view.
Meanwhile, hinting at ongoing eviction beginning from Chandranagar on August 24, Capital Complex DC Prince Dhawan said, “We have fixed a deadline to clear all structures along RoW and handover Chandranagr-Papu Nallah stretch latest bySeptember 12 next to the executing agency.
On school issue, he clarified that the board formed to grant compensation for structures falling outside RoW has already givenRs 45 as compensation including for RCC boundary wall, CC platform, boulder wall, two SPT buildings and RCC water tank. The fund is lying with education department which could be used to build two class rooms. Capital Complex DDSE has been directed to make interim arrangement to ensure that the education of students is not disturbed.
He urged all to cooperate with the district administration for smooth eviction.