GoAP to move GoI on cost hike: CM

PGCIL working to boost power scenario

ITANAGAR | Aug 31 | The Cabinet Committee on Economic Affairs, headed by Prime Minister Narendra Modi, had approved comprehensive scheme for strengthening transmission & distribution (T&D) systems (CSST&DS) in Arunachal Pradesh along with Sikkim at an estimated cost of Rs.4754.42 crore. An MoU was signed between PGCIL and Government of Arunachal Pradesh for implementation of the scheme in the state in February 2015 at an estimated cost of Rs 3199.45 crores.

Thus, Chief Minister Pema Khandu today reviewed the ongoing power transmission and distribution system being implemented by Power Grid Corporation of India Limited (PGCIL).

While highlighting details of present status through a power point, PGCIL CMD I S Jha informed that 29 transmission lines (1917-km) and 70 distribution lines (1923-km) are being laid covering the entire state. In all 94 sub-stations are to be set up under the scheme of which works of 61 are in full swing after awarding contracts.

Informing that lands for 38 sub-stations only have been made available by the GoAP, Jha sought land allotment for the rest soon. “We need lands for 33 sub-stations on priority, necessary to further the transmission & distribution lines,” he said.

Process of awarding contracts for rest sub-stations are on, Jha said and admitted that due to difficult terrains and other factors response were few. He cited few hurdles, like forest clearance and compensation issues hampering speedy laying of transmission & distribution lines, to which the CM assured to take up with authorities concerned and local administration.

On the issue of hiking estimated cost due to cost escalation, Khandu said the GoAP will impress upon the Centre about it as a review of the scheme is under consideration by the Centre.

Power department raised issue of capacity building of its officials as the project on completion would be handed over to the department for running and maintenance. Informing about capacity building provision, Jha assured help to avail it.

Only 5 out of 20 Arunachal Pradesh districts were connected to transmission network of 132/220 KV Till 2014. The 33-KV system is the backbone of state’s power distribution system. Due to low population density spread over its geographical area of 84,000 sqkm, state’s power demand is scattered over vast areas and distances. Hence, the necessity was felt to provide 132-KV connectivity in the state for proper voltage management and lower distribution losses.

Chief secretary, power & finance commissioners, power CEs and PGCIL representatives were present. (PRO)