By A O News Service
ITANAGAR | Oct 18 | Terming Arunachal Pradesh being an organic state by default, Chief Minister Pema Khadu informed the house during question hour that Ghaziabad-based National Centre for Organic Farming (NCOF) has consented to set up its sub-centre in the state at the initiative of the GoAP.
Responding to a supplementary from Takam Pario, Khandu said that there are 13 KVKs besides horticulture training centre at Dirang which are providing training to farmers.
Organic cultivation: On Pario’s query on organic status, Agriculture and Horticulture Minister Wangki Lowang earlier said that the GoAP had launched organic mission on 15.04.17 and progressing fast with trained agriculture officers.
To supplementary question from Tanga Bylaing, Khandu agreed that horticulture is the backbone of the state, said that he has decided to bring agriculture & allied sector under one umbrella with single secretary and director to reap the benefits.
PMGSY projects: Resending to a question from Tapang Taloh, RWD Minister Kumar Waii said 1003 PMGSY projects have been sanctioned and executed through tender bidding process.
Responding to Tanga Byaling’s supplementary, Waii said many road are damaged by natural calamities and restored.
Teachers’ shortage: Responding to supplementary that Borduria school opened in 1948 and upgraded to HS School in 2009-10 has been facing shortage of teachers, Education Minister Honchun Ngandam said shortage of teachers is a common problem in all state schools in the state. In all 100 primary & upper primary and 29 secondary schools have been upgraded since 2003-04 but without creation of any posts, Thus, at the initiative of CM Khandu 1,500 posts of teachers is likely to be created by the Cabinet for early recruitment. The present GoAP being serious would find the solution soon, he added.
Bobia PWD SE office: Responding to a supplementary from Nabam Tuki on link road to PWD SE office at Bobia under Sagalee sub-division, DyCM-cum-PWD Minister Chowna Mein said fund provision of approximately Rs 3.5 crore for road would be created in next financial year. However, Tuki sought additional Rs 13 lakh for electricity in revised estimate to make the office functional.
Hydel project: On Pario’s supplementary on Pagu hydropower project, CM Kandu said that the 2-MW project was sanctioned in 2008-09 at an estimated cost of Rs 22.74 lakh but has been inordinately delayed due to damages by rainfall and land litigation which escalated its cost to Rs 32.77 lakh from and the GoAP provided funds including from RIDF, he said, adding 78% of the project is complete so far.
On his query about completion target, CM said that such project should be completed by two years but assured to take up with department to speed up the process.
Tinsukia to Khonsa via Khonsa-Naharkatia road, built in 1956 by the people on self help basis, despite being the lifeline of Tirap and Changlang district has been deteriorating instead of seeing the light of the day, said Wanglong Lowangdong and wanted to know when fund would be completed for its completion: The PWD road would be taken up after the MoRTH sanctions fund.
Consenting to his concern, DyCM Mein said that the road was under the PWD but became NH 315A on being taken over by NH Development Authority. He informed that 9-km of this road has been approved by MoRTH and asked the state PWD to submit DPR which has been submitted for early sanction. The GoAP has urged MoRTH to approve rest 26-km of the road soon. MoS (Home) Kiren Rijiju, CM Khandu and he himself have written to the MoRTH for sanction of the entire road. But ministry officer said due to paucity of fund only 9-km road has been approved.
“The road was maintained through e-tender, but I have been severely criticized by a former home minister in facebook. However, maintenance would begin soon and condition would improve by next month,” Mein assured.
In a supplementary, Taloh urged the CM for fund to restore some portion of the hydel project washed away by heavy rainfall.