Tawang road still awful as BRO misses its 2016 target 

 

 *Tourism sector hit hard

By Pradeep Kumar

ITANAGAR | Oct 27 | The ramshackle condition of strategic 282-km Bhalukpong-Tawang road, lifeline for defence forces to Indo-China border, questions Border Road Organisation’s motto shramen sarbam sadhyetey (hard work conquers everything).

The BRO, set up in 1960 to develop the same road, needs to wake up to change its name to Brave Road Oraganisation to bring the much needed improvement. It is a fact that lack of road communication was one of the major causes for humiliating defeat of Indian Army during 1962 Chinese aggression. The army personnel had to march from Tezpur through this road to Tawang border, Zemithang, Bumla, Y and T junction where they had confronted with their Chinese counterpart PLA jawans.

Even after 55 years, the road is not a speedy passage for the defence forces, who cares for other commuters, including tourists. The BRO, a defence organisation, has been developing and maintaining the road by deploying its 42 Border Road Task Force. Conversion of the road into a double-lane was taken in March 2013.

Chinese roads all along the Indian border are highly developed. Its concrete road on the other side of Bumla facilitates driving at 60-80-km per hour while it is tough for Maruti gypsy to travel Tawang-Bumla road on Indian side. This indicates the defence preparedness of Beijing, contrary to Indian policy,  despite China’s India encircling policy. What would be the consequence in case of any eventuality? Should Home Minister Rajnath Singh’s recent statement ‘China no more considers India weak’ be a reprieve?

Of course, maintaining the road has been a tug-of-war between the nature and the BRO. The Bhalukpong-Tawang road was smoothly playable in June last but the massive impact of monsoon led to hillock slip and landslides at least at 17 points blocking the road for months. The works of the road to convert it a double-lane is progress in full swing. Single-lane black topped road and concretization of the other lane up to Jaswant Garh is visible while some patches have either been  totally washed away or deteriorated with potholes for lack of maintenance. The 35-km Tippi-Chessa stretch has been not been totally washed away leaving behind feet-depth mud posing tough challenges to drivers, while works still continues in right earnest in rest patches.

When BRO has proved its expertise by building 50,000-km road against all odds by maintaining high standard during its 54, it needs to take a cue from  Darjeeling to gain knowledge on hilly road technology. Despite much higher rainfall, the hill station roads are not damaged for adopting World Bank and ADB prescribed technology. The BRO should add to skill kitty on hill road technology, which was appreciated and accepted by Union MoS for MoRTH Mansukh L. Mandaviya, when his attention was drawn to the fact at Itanagar on Sept 13, 2016.

 

Bhalukpong-Tawang road to

be complete by 2016: DG

BRO   Director General Lt. Gen. R M Mittal had told this editor at Naharlagun on 21.01.15 that the strategic 317.52-km Chariduar-Bhalukpong-Tawang road executed by  the BRO will be completed by 2016 to set at rest the concern over the slow work progress since 2008.

“I saw the BRO engineers and personnel working with commitment during my inspection at Tawang, Tenga and Bomdila which gave me confidence of completing the important service road by 2016,” the DG, who completed his maiden five-day stock taking trip to Arunachal Pradesh since taking over charge on 15.12.14, told this editor in an exclusive interview, before leaving for New Delhi.

It would be worth mentioning here that Tawang legislator Tsering Tashi had recently expressed deep concerns over the slow progress of the road that had affected the movement of the masses, the defence forces and badly hit the high potential tourism sector of the region which was later raised in the state Assembly.

Bomdila MLA Japu Deru, raising the issue on the floor of the house on 31.07.14, had observed that completion of the road would provide connectivity to the Indo-Sino border and said, “The road built in 1962, after the Chinese aggression, was still in dilapidated condition even after 52 years”.

When pointed out that Prime Minister Narendra Modi had also attached priority to the development of border roads in Arunachal, the DG said, “I decided to visit this Himalayan state first as of the 18 BRO road projects, where eight are in NE region including four in this state. Thus, I wanted to take stock of everything to accelerate the process by removing the hurdles and solving various difficulties in execution”.

Lt. Gen. Mittal along with Maj Gen. U S Dadu, BRO’s NE incharge and Project Arunanak CE Brig. H K Pokhariyal had inspected ongoing works at Tama Chung Chung and Reddi in Upper Subansiri district part of 221-km Daporijo-Taksing road along China border on 20.01.15.

The BRO has a proposal to  temporarily hire about 1,000 diploma holder engineers from all over India for which the CEs have been given guidelines to visit the polytechnic institutes. The fresh engineers will sharpen their skills and widen their knowledge with BRO expertise to make them successful entrepreneurs. That was why it was decided the process to hire local engineers by the BRO had begun, he had decided.

Road along China: Describing the ambitious 2000-km border road from Mago-Thingbu in Tawang to Vijaynagar in Changlang district announced by Union MoS Kiren Rijiju a dream project but a great necessity for providing land connectivity to the border guarding forces as well as the border villagers, he committed to be part of the building process, if entrusted with the responsibility.