Land acquisition is state subject: MoRTH ADG

 

By Our Staff Reporter

ITANAGAR | Nov 13| Land acquisition is a state subject but surprsingly the process has been delayed even after payment made to the GoAP, Union MoRTH  additional DDG I K Pandey commented on delay in execution of Potin-Pangin road.

Addressing a meeting here today to review various state road projects  attended by representatives of National Highway Infrastructure Development Corporation Ltd, state PWD and others, he disclosed that 150-km land has been acquired for the road and hoped the rest would be acquired soon as every problem has a solution.

On  important  road projects under Trans-Arunachal Highway and Central Road Fund being executed by the PWD, NHIDCL, BRO  and MoRTH and others under ‘Bharat mala’  scheme, he said that most project are not being implemented as per the schedule  should be expedited by the authority concerned. The targets are yet to be achieved so far due to delay, may be for  many reasons, he observed and urged all those involved to work with commitment to provide the much needed  connectivity to people of this frontier state with GoI resources. He suggested several measures including use of technology to smoothen execution to build life line for the people.

On liability of flood restoration work taken up during last monsoon, he said that all requests and proposals should be sent with proper documents for consideration of the MoRTH.

NHIDCL DGM Hibu Tadey said that many roads are ongoing including by PWD and BRO. The NHIDCL in executing 1061-km of roads including  a Bharat Mala project ear Myanmar border.

Terming the MoRTH role pivotal in infrastructure development,  PWD commissioner Belatee Pertin said that delay in land acquisition for  Potin-Pangin road, the  project is reportedly on the verge of termination. This TAH portion needs special attention, he said and urged the ADG to ventilate state problems to the GoI.

All land belong to tribal community, which are regulated by traditional land holding system, Pertin said, adding the GoAP leases out to user agency as a witness. The GoAP approaches the public in case of any road plan, he said. The regional officer here holding charges of Assam and Arunachal affects proper coordination, he said and suggested a separate MoRTH RO for Arunachal as has been written by the GoAP but no action so far.

Hinting at limited working season between October to March, he said that heavy landslide and disruption of roads and bridge were recorded this year. There was no time to call tender though restoration works were taken up on temporary basis at a cost of Rs 10 crore but more than Rs 112 crore is still due and urged the ADG to reimburse the amount due to the contractors.

Pandey, given the responsibility for NE, West Bengal and Gujrat and on his maiden visit to the state, told this daily that many schemes are being executed under Bharat Mala scheme to meet high expectation of NE people.

On reported termination of Potin-Pangin project, he said that it cannot be said right now as it needs clearance at various stages.  Fault lies solely on contractor for not taking up the work due to land acquisition  which should be sorted out, depending on its merit, he said, adding two road project in Eastern Arunachal so far have been terminated for inordinate delay. Pertin interrupted to say that Potin-Pangin project abrupt termination would not bode well and the GoAP should be given a chance to decide on a positive note.

When his attention was drawn to pathetic condition of Potin-Ziro road phase, he said that there is no fund for flood damaged rectification work. However, renovation work and is under progress with around Rs 10 crore allocation and due to be completed by December 17.

Informing about two terminated, Eastern Zone (highway) S E  S. Sumnyan said that Khonsa-Tissa-Longding in Tirap district awarded in 2012 whose half  portion could not be completed by the contractor in five years and terminated in April 2017. The DPR under EPC mode is being prepared for the project.  The DPR is being prepared for terminated Lalpur-Monmo-Changlang project, he said.

On 90-km Tinsukia to Khonsa portion of Hukanjuri-Khonsa road connecting two states, declared in 1992 NH-315 (A)which, he said that 35-km stretch falls in Tirap district and 9-km has been considered under annual plan, he said and urged  the ADG to consider the balance stretch of road.

RO Singh, SE (highway) Duggum Ete elaborated all projects taken, while representatives of SUSHEE Infra & Mining Ltd,  TK Engineering Consortium Pvt Ltd, agency implementing Dibang Bridge, Putin-Panging road, engineers, consultants and other officials were present.