AGARTALA | Apr 10 | The GoAP is contemplating to cancel memorandums of agreements (MoAs) signed with various private firms to develop over 130 hydropower projects in the state for their failure so far to make visible progress, Deputy Chief Minister Chowna Mein today said.

Arunachal Pradesh boasts of estimated hydropower potential of about 60,000-MW, almost 40% percent of India’s total potential. However, various factors, including protests by affected tribal communities and difficulty in getting environmental clearances from the Centre for which only the state now has one functioning major hydropower project– Stage I of  405-MW Ranganadi Hydro Electric Project.

While addressing first meeting of ‘Niti Forum for North-East’, Mein said that although the GoAP had signed agreements with power developers to tap at least 40, 000-MW of power but  only 475.11 MW has been harnessed so far, amounting to only 0.82%.

Two more projects- 600-MW Kameng HEP and 110 MW Pare HEP are scheduled to be commissioned within this month, taking total power generation to 1185.11-MW (2.04%).

Mein today said that Most power developers are struggling to move ahead with plans to proceed with construction of the projects “due to mandatory clearances involving many departments of state and Centre”.

However, Mein urged the Centre to provide required support to power developers and the state”.
However, he also informed that the state government is “contemplating to issue termination notices to those developers who have not adhered to timelines in the memorandums of agreement”.

Mein said that the agreements can be terminated and the projects awarded to PSU units, like NEEPCO, no operating Ranganadi HEP and two other projects scheduled to be commissioned later this year.

However, he said that Union Power Ministry could constitute an expert committee and make estimates for a ‘viability gap fund’ to be given to power developer by the ministry or DoNER Ministry.

Lack of connectivity is the biggest obstacle and challenge to holistic development of NE, he said.