ITANAGAR, Aug 09: With the panel board of 132/33 KV transformer No 1 of 132kv substation at Daporijo getting burnt on Wednesday midnight due to flashover of voltage, Power Minister Tamiyo Taga a meeting here today reviewed the situation including damages caused.
The fire was doused with timely intervention of fire brigade and police but darkness has plunged over Daporijo and other central and eastern parts of the state as supply from Ziro was shut down as a precautionary measure, according to an official release.
However, supply to other parts beyond Daporijo was restored today by isolating Daporijo. It was decided to avail necessary fund from disaster management for immediate restoration. But, Taga directed the departmental officials to immediately float tender for annual maintenance contract (AMC).
The extra high voltage substations at Aalo and Deomali are at very vulnerable stage and needs immediate maintenance through special funding, he pointed out.
SE T.K. Tara & EE(transmission) Sange Phuntso have been deputed to assess the damages and prepare necessary reports for its immediate restoration while another technocrat team has been deputed to find out the cause of the mishap.
Power commissioner GS Meena, all power CEs and SE (transmission), among others, attended the meeting.