Payment made road work incomplete: KYC

KAMBA, May 29:  The Keak Youth Club (KYC) on Wednesday in a three-point memorandum drew attention of West Siang RWD executive engineer towards long pending PMGSY road project from Keak village to Kesi Tali village.

The project was targeted to be complete within November 10 last year as per relevant documents obtained through RTI, the KYC claimed and alleged that 50% payment was given to contractors of M/s T.G Enterprises. However, only 30% works have completed till date while the work progress is in snail phase despite in total violation of set guidelines of the state government.

It urged the EE to initiate necessary action to expedite the process as per DPR for early completion.