Potom inspects ongoing NH works, work progress 61%: EE Tath

By Staff Reporter

ITANAGAR, Dec 02: Additional district magistrate (ADM)-cum-chief estate officer Talo Potom inspected NH-415 from Chandanagar to Akashdeep with PWD (highway) engineers and TK Engineering Consortium Pvt. Ltd representatives.

Potom, while talking to media persons, said that the work motion was disturbed and slowed by the nature besides several hindrances on the said stretch which could have been resolved.

Huge works are still pending while several hindrances are yet to be removed, he said and hoped that the works with quality would gain momentum with monitoring and supervision, but the agency TKE should be given free hand.

The inspecting aims at proper utilization of several public utilities, like electric poles, he said, adding survey is being conducted to make use of available space of old road after alignment for parking and other purposes. After inspection a report with suggestion would be submitted to the chief secretary soon for a direction.

On complete eviction along the NH-415, he said that the road was under Capital district administration and several stretches are yet to be evicted for which several utility services have neither been shifted nor replaced by department and individuals concerned, he said.

“Several review meetings were conducted to speed up works, but physical progress is around 61%. There are two stretched which hopefully would be completed by January 10 while the restriction of traffic movement along Itanagar-Naharlagun during night hours may continue till January 20.  Formation cutting may not be complete but there would be no risk factor for the work to continue.

“The quality control, alignment and finished road level are being monitored and supervised by quality engineers. Hopefully everything would go well if the commuters cooperate with the TKE for works on war footing. I have apprised the ADM about work progress, other issue and including court cases so as to inform to the higher level for immediate resolution and the work progress does not get any hindrances,” PWD (highway) Nirjuli division EE Nani Tath said.