ITANAGAR, Jan 23: Civil Aviation Minister Nakap Nalo assured all help & support of the GoAP to steer all activities for early completion of Hollongi Airport, a dream project, for much awaited air-link to state Capital, while chairing a meeting here on Thursday, to review work progress.
While highlighting the status, NE region Airports Authority of India executive director Sanjeev Jindal said that the first phase of work of pavement, watch tower, perimeter road etc. for 2300-m runway to operate A320, to being in February first week next, while tenders for 2nd phase terminal building and others would be finalized in April next.
shifting of 11 KV LT power line passing through the site will be completed by March next and works for supply of bulk water & power, boundary wall, 4-lane approach road to begin in February next, state work agencies said.
Detailed survey to shift 132 KV Gobpur-Nirjuli transmission line is over and process to obtain forest clearance for alternate route in progress, said POWERGRID senior GM C. Borkotoky. Civil aviation director Tamiyo Tatak, CEs of PWD, power, PHE&WS, UD & Housing with all stake holders were present, according to an official release.