NH-415 (package-A) work status reviewed

ITANAGAR, Sept 03: The status of construction of Itanagar -Banderdewa four-lane NH-415 (package-A) was review in a meeting attended by senior highway engineers here on Thursday to work out strategy for early completion.

The project was started in September-2017 with three-year completion target but, its work progress suffered due to COVID-19 pandemic and prolonged monsoon. However, physical achievement as on 01.09.20 was 72.46 % against all odds.

The formation cutting of the stretch has been almost complete except a small patch, near Shiv Mandir for filling up the culvert bridge in between Shiv Mandir and Dree ground. Other works, like protection walls, drains and cover drains, culverts and carpeting will be taken up and completed during coming working season. With the relaxation of SoPs, the concessionaire is bringing in more labourers from nearby states to accelerate execution.

It may be recalled that the state government had sanctioned Rs. 82.85 crore for improvement of capital roads and for repair & maintenance of road & bridges in and around the capital region for which tender process has been completed for the work to commence soon.

The Department has been directed to take up the work on a mission mode and strictly adhere to timeline. It has been decided to review work progress every fortnightly. The highway engineers were advised for timely maintenance of  commuters to travel smoothly.