CM reviews PMGSY projects | Vehicles to reach Vijoynagar by March end: RWD

Vijoynagar road on DC’s top priority

AONS adds: The construction of 157-km Miao-Vijoynagar road is my top priority agenda, Changlang deputy commissioner Dr Devnash Yadav had told this daily over telephone on May 13 last.

Land-locked Vijoynagar, spread across 8,000-sqkm, called Daudi by local residents Lisu (Yobin), located along India-China-Myanmar tri-junction, an administrative HQs in Changlang district is the remotest inhabited land of India but without any road connectivity even 74 years after independence. It takes about six days to reach Miao by walk.

The 213-km Nampong-Vijoynagar road built in 1972 was motorable till 1980 and then state Lt Governor KAA Raja had reached Vijoynagar with a fleet of 12 jeeps, the first and last vehicles seen there.

The  road is still a mirage despite sincere efforts of former Changlang DC Dr. S. B. Deepak Kumar, who had walked through this road in December 2009, former governor Gen (Retd) JJ Singh in March 2012 (opened temporarily after 36 years), Miao MLA-cum present Minister Kamlung Mosang, present Governor Brig (Retd) B D Mishra and Chief Minister Pema Khandu. And Vijoynagar residents presently take about five to six days by foot to reach Miao. However, the RWD would create a milestone with construction of this road.

 

ITANAGAR, Sept 30: At least SUVs and four-wheel drive vehicles would reach Vijoynagar, by next March end, rural works department (RWD) engineers assured Chief Minister Pema Khandu, who was reviewing ongoing PMGSY projects here on Wednesday.

The CM assured to adjust gap funding for the road and suggested RWD to speed up works on priority and maintain continuity.

Expressing concern over the slow progress of several PMGSY projects, he directed the RWD to call a meeting of all road contractors engaged across the state, preferably in October first week, to review status of each project. He urged RWD Minister Honchun Ngandam to chair the meeting and take report on status of each road project, but the defaulters should be held responsible, he said with assertion.

Total 933 projects of 9744-km length of sanctioned 1,311 roads of about 13868-km have been completed till date. However, the Centre has set 2020-21 fiscal year as target to complete 4850-km roads, as per official records.

“Call all contractors and let them explain in person challenges facing them and reasons for delay if any,” Khandu advised and said that the state cannot go for Part-III before completing Part-I and II which would  deprive many villages of road connectivity.

PMGSY roads’ maintenance sprang up as one of the major challenges faced by the RWD. PMGSY roads being length-wise largest road network and located in rural and remote terrains, are badly affected by the monsoons annually. However, as funds for maintenance are not easily available as it comes under state subject, Khandu sought a mechanism to resolve the issue from engineers led by chief secretary.

While taking stock of Miao-Vijoyanagar PMGSY road, he assured to adjust gap funding for the road. He suggested RWD to take up the road on priority and maintain continuity. He was assured by the department officials that by end of March next at least SUVs and four-wheel drive equipped vehicles would reach Vijoynagar.

Meanwhile, the CM along with Skill Development Minister Tumke Bagra,  reviewed status of Pradhan Mantri Kaushal Vikas Yojana, when both were informed that skill development & entrepreneurship  department (SDED) has set a target to skill 14,434 persons by 2021 and 8,631 have been trained till date of whom  4,872 got placement.

As per data, more youths are opting for training in electronics and hardware, followed by tourism and hospitality and media and entertainment. The CM suggested the SDED to focus on high-end skill development, especially in tourism and health care services besides training for excavator operators, call centers, etc, which have better scope of employment within the state in future. (CMO)